Handed over the renovated dissecting room for Jahn Ferenc Hospital

Handed over the renovated dissecting room for Jahn Ferenc Hospital

We handed over our first complex autopsy room renovation, where we built in our new developed autopsy table with air absorber system. The renovation started in the beginning of 2010 and the project took 10 weeks. The new autopsy room with many new features (Granite work surface (adjustable height from 700 to 950 mm), stainless steel frame structure, air-conduction with adjustable direction and volume, air removal under the brim of the work surface) became the most modern autopsy room of Hungary.

Details of the project >>

Dissecting room before renovation
Demolition - 1. step
Demolition 2. step
Building
Dissecting tables
Climate control and video intercom
Technology transfer